SE workshop (TEFI+PREMP for DIF+SPEC)

Europe/Stockholm
Norma S6F3 (Day 1); Kebnekaise S7F2 (Day 2) (ESS site)

Norma S6F3 (Day 1); Kebnekaise S7F2 (Day 2)

ESS site

Odarslovsvagen, Lund, SE
  • Tuesday, 22 January
    • 09:00 10:55
      Overview: Goals of meeting, consolidate INST perspective, SAD perspective
      • 09:00
        Introduction and goals of meeting 5m

        Introduction and overview or SES series of meeting.

        Speakers: Arno Hiess (European Spallation Source ERIC), Malcolm Guthrie (European Spallation Source ERIC)
      • 09:05
        BIFROST SE needs for early science 10m

        Brief, targeted overview of SES needs, during commissioning (cold and hot) and early science

      • 09:15
        CSPEC SE needs for early science 10m

        Brief, targeted overview of SES needs, during commissioning (cold and hot) and early science

      • 09:25
        DREAM SE needs for early science 10m

        Brief, targeted overview of SES needs, during commissioning (cold and hot) and early science

      • 09:35
        MAGIC SE needs for early science 10m

        Brief, targeted overview of SES needs, during commissioning (cold and hot) and early science

      • 09:45
        TEFI: Summary of SEE - equipment list and schedule 20m

        Summary of SE systems and current schedule (within construction)

        Speaker: Alexander Holmes (European Spallation Source ERIC)
      • 10:05
        PREMP: Summary of SEE - equipment list and schedule 20m

        Summary of SE systems and current schedule (within construction)

        Speaker: Malcolm Guthrie (European Spallation Source ERIC)
      • 10:25
        Discussion: Does list match needs, what is priority, Day 1 or later? 30m
    • 10:55 11:15
      Coffee 20m
    • 11:15 12:00
      TEFI: Detailed plans, spec and schedule of equipment

      Overview of TEFI SE systems

      • 11:15
        Ultra low temperature 15m

        confirm top level spec
        identify commonality between intstruments
        what interfaces needed (mechanical, software)
        usability, ergonomics, safety

        Speaker: Alexander Holmes (European Spallation Source ERIC)
      • 11:30
        General cryo/cryofurnaces 15m

        confirm top level spec
        identify commonality between intstruments
        what interfaces needed (mechanical, software)
        usability, ergonomics, safety

        Speaker: Alexander Holmes (European Spallation Source ERIC)
      • 11:45
        Furnaces 15m

        confirm top level spec
        identify commonality between intstruments
        what interfaces needed (mechanical, software)
        usability, ergonomics, safety

        Speaker: Alexander Holmes (European Spallation Source ERIC)
    • 12:00 13:00
      Lunch 1h
    • 13:00 14:55
      TEFI: Detailed plans, spec and schedule of equipment (cont')

      Overview of TEFI SE systems

      • 13:00
        Non-ambient sample changers 15m

        confirm top level spec
        identify commonality between intstruments
        what interfaces needed (mechanical, software)
        usability, ergonomics, safety

      • 13:15
        Motion axes 15m

        confirm top level spec
        identify commonality between intstruments
        what interfaces needed (mechanical, software)
        usability, ergonomics, safety

      • 13:30
        Magnets 15m

        confirm top level spec
        identify commonality between intstruments
        what interfaces needed (mechanical, software)
        usability, ergonomics, safety

      • 13:45
        Vacuum tanks & magnetic considerations 30m

        to what extent can equipment be shared between floor and flange mounted instruments?
        practicalities and safety for vacuum mounted SEE
        *stray field issues, particularly wrt polarised neutrons

      • 14:15
        TEFI roles and responsibilities discussion 20m

        who does what during project stages?
        - Detailed design
        - procurement
        - installation/integration
        - maintenance
        - normal operation

      • 14:35
        TEFI Schedule 20m

        *outline of delivery schedule
        * delivery date (cold vs hot commissioning)
        * does SES impact instrument critical path.

    • 14:55 15:15
      Coffee 20m
    • 15:15 16:55
      PREMP systems: Detailed plans, spec and schedule of equipment
      • 15:15
        Gas, Liquid and Clamp cells (10min talk, 10 min discussion) 20m

        confirm top level spec
        identify commonality between intstruments
        what interfaces needed (mechanical, software)
        usability, ergonomics, safety

      • 15:35
        Paris-Edinburgh systems (10min talk, 10 min discussion) 20m

        confirm top level spec
        identify commonality between intstruments
        what interfaces needed (mechanical, software)
        usability, ergonomics, safety

      • 15:55
        Diamond-anvil type cells (10min talk, 10 min discussion) 20m

        confirm top level spec
        identify commonality between intstruments
        what interfaces needed (mechanical, software)
        usability, ergonomics, safety

      • 16:15
        PREMP Schedule, roles and responsibilities 20m

        Schedule:
        *outline of delivery schedule
        * delivery date (cold vs hot commissioning)
        * does SES impact instrument critical path.
        who does what during project stages?
        - Detailed design
        - procurement
        - installation/integration
        - maintenance
        - normal operation

      • 16:35
        Mechanical interface 20m

        floor and flange mounted interfaces

    • 16:55 17:15
      Day 1 Wrap up

      Summarise conclusions, consolidate notes, plan for Day 2

  • Wednesday, 23 January
    • 09:00 09:30
      Example operational Scenario 1: BIFROST 30m

      Possibility: Installation of equipment on BIFROST

      A role play, where we will examine all stages of installation:
      - transporting equipment from staging area
      - location of auxiliary equipment
      - location of utility supplies
      - ergonomics of installation
      - safety considerations

      Speaker: Liam Whitelegg (DTU Copenhagen)
    • 09:30 10:00
      Example operational scenario 2: MAGIC 30m

      Possibility: install magnet on MAGIC

      A role play, where we will examine all stages of installation:
      - transporting equipment from staging area
      - location of auxiliary equipment
      - location of utility supplies
      - ergonomics of installation
      - safety considerations

      Speaker: Xavier FABREGES (Laboratoire Léon Brillouin)
    • 10:00 10:30
      Discussion: Practicalities cave design 30m
      • ease of access (personnel and equipment)
      • utility placement, cable length etc.
      • installation scenarios
    • 10:30 10:50
      Coffee 20m
    • 10:50 11:20
      Discussion: Health and safety interfaces 30m

      How does cave design interact with SEE to ensure safety
      Impact on operational models
      facilitating lone working
      Need for interlocked SEE

    • 11:20 12:00
      Summary of morning discussions 40m

      conclusions
      allocate actions
      decide on write up